Project No 2004/LT/16/C/PT/003
THIS PROJECT IS HELPING TO REDUCE ECONOMIC AND SOCIAL DISPARITIES AMONG THE CITIZENS OF THE EUROPEAN UNION
 
 
Project No 2004/LT/16/C/PT/003
Development of IXB Transport Corridor in the Years 2004–2006
 
 
International corridors are the most important part of Lithuanian Road network. Though there are still (many) sections falling behind the requirements for transport corridors. The main objective of this project – to reconstruct these sections and to ensure safe and convenient traffic conditions in conformity with the level of traffic volume, road significance and international standards. It is anticipated that the benefit of IXB transport corridor reconstruction is as follows:
·          better and higher quality road traffic conditions;
·          reduced accident rate;
·          reduced vehicle operating costs;
·          strengthened road pavement structure;
·          slower pavement degradation and longer pavement service life;
·          lower costs of road repair and routine maintenance.
 
Cost of Project
202,022,875 LTL
including:
 
  • Cohesion Fund
158, 804,630 LTL
    
 
  • Road Maintenance and Development programme
43,218,245 LTL
     
 
 
 
Start date of Project
01/06/2004
End date of Project
31/12/2010 
 
 
 
The Project includes:
-         strengthening of road pavement – 20.12 km;
-         strengthening and widening of road pavement – 37.98 km;
-         road reconstruction – 83.84 km;
-         new road construction – 4.0 km;
-         construction of pedestrian – cycling paths – 4.719 km;
-         road illumination – 7.07 km;
-         construction of grade-separated pedestrians crossings – 7 units;
-         reconstruction of bridge or bridge deck – 21 unit;
-         construction of crash barriers – 46.97 km;
-         construction of grade-separated intersection – 3 units;
-         construction of noise protection walls – 1.38 km;
-         construction of wire net fencing – 27.32 km;
-         construction of underpasses for wild animals – 2 units.
 
 
Contracts of the Project
Anticipated Contracts in the Project – 6
 
Contracts data
 
Works Contract
No 2004/LT/16/C/PT/003-D01
Date of Contract signing
13 October 2004
Contractor
AB Kauno tiltai
Value of works carried out
30,478,919 LTL
Date of completion
1 November 2006
 
 
Works Contract
No 2004/LT/16/C/PT/003-D02
Date of Contract signing
10 June 2005
Contractor
AB Kauno tiltai
Value of works carried out
61,822,424 LTL
Date of completion
30 September 2006
 
 
Works Contract
No 2004/LT/16/C/PT/003-D04
Date of Contract signing
12 September 2006
Contractor
AB Kauno tiltai
Value of works carried out
83,698,094 LTL
Date of completion
 
Works Contract
Date of Contract signing
Contractor
Contract value
Date of completion
30 September 2007
 
No 2004/LT/16/C/PT/003-D03
30 June 2009
AB Kauno tiltai
22,339,635 LTL
30 June 2010
 
 
Service Contract (Technical Supervision)
No 2004/LT/16/C/PT/(001-005)-TP01 (8871063/2004/16/41)
The Contract, financed according to five EC Decisions for the relevant part of Technical Supervision, was signed
Date of Contract signing
11 August 2004
Contractor (Supplier)
VĮ Problematika
Value of services provided
2,616,519 LTL
Date of completion
11 April 2007
 
Complementary Service’ Contract (Technical Supervision)
No 2004/LT/16/C/PT/(001-005)-TP02/S-147
The Complementary Contract of Technical Supervision of construction works  for the road sector projects ( No 2004/LT/16/C/PT/001-005), financed by the funds of LR budget, was signed
Date of Contract signing
11 April 2007
Contractor (Supplier)
VĮ Problematika
Price of relevant Contract part
1,067,284 LTL
Date of completion
1 February 2008
Updated 12-11-2009
top
Development of Roads (E85 Lyda–Vilnius) and E272 (Vilnius–Panevėžys–Šiauliai–Palanga) of Transeuropean Transport Network
 
  
Project “Development of Roads (E85 Lyda–Vilnius) and E272 (Vilnius–Panevėžys–Šiauliai–Palanga) of Transeuropean Transport Network. Reconstruction and reinforcing of cover of Road  Vilnius–Panevėžys–Šiauliai–Palanga (I stage)”
 
The project is financed from the European Union Structural Assistance funds 2007–2013 according to the Economic Growth Action Plan Priority 5 “Development of Trans-European Transport Networks“  instrument VP2-5.1-SM-01-V “Enhancement of the Permeability of Trans-European Road Infrastructure. Improvement of Technical Parameters".
 
Additional TEN-T links make the important part of Lithuanian road network. Roads E85 (Lyda–Vilnius) and E272 (Vilnius–Panevėžys–Šiauliai–Palanga) of Transeuropean Transport Network cross the territory of Lithuania from the southeast to the west, connecting border post of Šalčininkai with Klaipėda and Palanga in the west. Roads E85 and E272 in the territory of Lithuanian Republic pass along the main roads: A15 Vilnius-Lyda; A2 Vilnius-Panevėžys; A17 Panevėžys bypass; A9 Panevėžys-Šiauliai; A11 Šiauliai-Palanga.
 
There are still many sections falling behind the requirements for traffic volume and axle load. The main objective of this project – to reconstruct these sections and to ensure safe and convenient traffic conditions in conformity with the level of traffic volume, road significance and international standards.
 
After having evaluated possible alternatives an utmost attention will be devoted to reinforcing of cover of Road E272 Vilnius–Panevėžys–Šiauliai–Palanga, to reconstruction of bridges, to implementation of traffic safety and environmental measures.
Implementation of works planned in the budget of the years 2007-2013 of the Program of European Union for structural assistance on the roads E85 and E272 will result in the following benefit:
·        improved image of Lithuania as a Transit State;
·        improved road traffic conditions for the international traffic, passing from Aleksandropol, Budapest, Černovcy, Lyda to Klaipėda, also inside the country;
·        reinforced cover construction allows to hold a maximum pressure limit on the axis of 11,5 t instead of 10t;
·        suspended rapid degradation of cover;
·        longer cover service life;
·        eliminated deep tracks which present a danger to the safe traffic;
·        lower costs of road repair and routine maintenance;
·        reduced vehicle operating costs;
·        reduced accident rate;
·        shorter travel time;
·        reduced negative environmental impact.
 
Primary cost of Project
70,449,000 LTL
including:
 
  • Cohesion Fund
42,000,000 LTL
 
 
  • Road Maintenance and Development programme
28,449,000 LTL
 
 
Start date of Project
14/09/2007
Primary End date of Project
12/2009
 
The Project includes:
-         strengthening and widening of road cover – 38.71 km;
-         reconstruction of bridge and viaducts – 14 units;
-         construction of pedestrian underpass – 1 unit;
-         construction of crash barriers – 3.54 km;
-         construction of wire net fencing from pedestrians– 3.37 km;
-         installation of lighting on the section of 2.74 km;
-         construction of crash barriers – 4.83 km;
-         construction of underpasses for wild animals – 2 units
-         construction of wire net fencing from wild animals– 20.5 km;
 
Contracts of the Project
 
 
Two contracts were signed and one contract will be.
 
Contracts data
 
Works Contract
Contract No 1 (S-1061)
Date of Contract signing
15 October 2007
Contractor
AB Panevėžio keliai
Value of works carried out
59,322,833.02 LTL
Date of completion
31 October 2008
 
 
Works Contract
Contract No 2 (S-1083)
Date of Contract signing
19 October 2007
Contractor
UAB Šiaulių plentas
Value of works carried out
16,096,401.15 LTL
Date of completion
30 November 2008
 
Works Contract
 
Contract No 3 (S-165)
Date of Contract signing
Contractor
Value of works carried out
Date of completion
27 May 2009
UAB Lemminkainen Lietuva
12,840,562 LTL
30 October 2009
 
Updated 29-04-2010
top
Reconstruction of Road E85 (Vilnius–Kaunas–Klaipėda) of Transeuropean Road Network
 
  
 
Reconstruction of Road E85 (Vilnius–Kaunas–Klaipėda) of Transeuropean Road Network.  Pavement reconstruction
 
The project is financed from the European Union Structural Assistance funds 2007–2013 according to the Economic Growth Action Plan Priority 5 “Development of Trans-European Transport Networks“  instrument VP2-5.1-SM-01-V “Enhancement of the Permeability of Trans-European Road Infrastructure. Improvement of Technical Parameters".
 
International corridors are the most important part of Lithuanian Road network. Though there are still sections, needed to be reconstructed to ensure convenient and safe traffic conditions in conformity with the level of traffic volume, road significance and international standards.
 
After performing of works foreseen in the strategic development program the infrastructure of IXB transport corridor, part of which the road E85 (Vilnius – Kaunas – Klaipėda) is, will be improved and the following benefits will be achieved:
·          improved image of Lithuania as a transit country;
·          improved traffic conditions;
·          reduced accident rate;
·          reduced vehicle operating costs;
·          strengthened road pavement structure;
·          slower pavement degradation and longer pavement service life;
·          lower costs of road repair and routine maintenance.
 
 
On 23 November 2009 the Agreement of financing and administration of the project No VP2-5.1-SM-01-V-01-007  “Reconstruction of Road E85 (Vilnius–Kaunas–Klaipėda) of Transeuropean Road Network.  Pavement reconstruction”  No 1F-155 was signed between the Lithuanian Road Administration under the Ministry of Transport and Communications, Transport Investment Directorate and the ministry of Transport and Communications of the Republic of Lithuania.
 
 
Cost of Project
102 843 456 LTL
including:
 
  • EU funds
90 264 376 LTL
 
 
  • Road Maintenance and Development programme
12 579 080 LTL (expenditures not eligible for EU financing)
 
 
 
 
Start date of Project
15/12/2006
End date of Project
30/04/2011
 
The Project includes:
-         strengthening and widening of road pavement – 23,23 km;
-         road illumination – 4,0 km;
-         reconstruction of bridge/viaducts – 5 unit;
-         construction of wire net fencing – 44,76 km;
 
 
Contracts of the Project
 
Four contracts for construction works, one contract for technical supervision and four contracts for technical design were signed.
 
 
Technical Design Contract
Contract No 1 (S-687)
Date of Contract signing
3 July 2006
Contractor
UAB Kelprojektas
Value of works carried out
483 293 LTL
Date of completion
30 March 2007
 
 
Technical Design Contract
Contract No 2 (S-219)
Date of Contract signing
298 March 2008
Contractor
UAB Saugvila
Value of works carried out
206 626 LTL
Date of completion
31 May 2008
 
Technical Design Contract
Contract No 3(S-537)
Date of Contract signing
7 August 2007
Contractor
AB Kauno tiltai
Value of works carried out
70,445,987 LTL
Date of completion
30 September 2008
 
Technical Design Contract
Contract No 4 (S-1072)
Date of Contract signing
29 April 2008
Contractor
AB Saugvila
Value of works carried out
204 659 LTL
Date of completion
30 Juner 2008
 
Works Contract
Contract No 1 (S-1194)
Date of Contract signing
12 September 2008
Contractor
AB Kauno tiltai
Value of works carried out
35 196 333,99 LTL
Date of completion
20 December 2009
 
Works Contract
Contract No 2 (S-138)
Date of Contract signing
13 April 2010
Contractor
UAB Švytėjimas
Value of the contract
6 935 398,75 LTL
Date of completion
29 September 2010
Works Contract
Contract No 3 part I (S-398)
Date of Contract signing
19 July 2010
Contractor
AB Kauno tiltai
Value of works carried out
18 499 999,00 LTL
Date of completion
19  July  2011
 
Works Contract
Contract No 3 part II (S-399)
Date of Contract signing
19 July 2010
Contractor
AB Kauno tiltai
Value of works carried out
28 894 691,56 Lt LTL
Date of completion
19  July  2011
 
 
Service Contract
(Technical Supervision)
 
Contract No S-117
Date of Contract signing
1 April 2010
Supplier
VI Problematika
Value of the contract
6 935 398,75 LTL
Date of completion
28 February 2011
 
Updated 02-08-2010
top
Development of the Road E262 (Kaunas–Zarasai–Daugpilis) of the Transeuropean Network
 
Project „Development of the Road E262 (Kaunas–Zarasai–Daugpilis) of the Transeuropean Network. Reconstruction of the Road and Pavement Strengthening (Stage I)“
 
 The project is financed from the European Union Structural Assistance funds 2007–2013 according to the Economic Growth Action Plan Priority 5 “Development of Trans-European Transport Networks“  instrument VP2-5.1-SM-01-V “Enhancement of the Permeability of Trans-European Road Infrastructure. Improvement of Technical Parameters".
 
International corridors crossing our country are the main part of the Lithuanian road network. Road E262 of the Transeuropian network, merging on Lithuanian territory with main road A6 Kaunas–Zarasai–Daugpilis, is one of the links of network of the European transport corridors. There are still some sections of this road falling behind the requirements for international roads. The main objective of the project is the improvement of road technical parameters, adapting them to the growing traffic volume, the improvement of traffic conditions, the preservation of harmony with environment.
 
After performing of works foreseen in the strategic development programmme for road E262 of the Transeuropian network the following benefits will be achieved:
·          improved image of Lithuania as a transit state;
·          improved road traffic conditions;
·          reduced accident rate;
·          reduced vehicle operating costs;
·          slower pavement degradation and longer pavement service life;
·          lower costs of routine maintenance.
 
 
Preliminary Cost of Project
119,200,000 LTL
including:
 
  • Cohesion Fund
62,900,000 LTL
  • Road Maintenance and Development programme
56,300,000 LTL
Start of the Project
14/09/2007
Preliminary end of the project
12/2009
 
The project includes:
 
-         strengthening of road pavement – 0.90 km;
-         widening of road pavement – 27.32 km;
-         strengthening and widening of road pavement – 10.57 km;
-         road illumination – 6.28 km;
-         erection of crash barriers – 4.83 km;
-         construction of wire net fencing – 17.81 km;
-         implementation of water protection measures – 4 units;
-         reconstruction of 4 bridges and 1 viaduct.
 
Contracts of the Project
 
 There are three work contracts signed. Contacts No 1 and No 2 are implemented. Works according to Contract No 3 are being performed.
 
Works Contract
Contract No 1 (S-1223)
Date of Contract signing
18th  December 2007
Contractor
AB „Kauno tiltai“
Value of works carried out
35,753,060.63 LTL
Date of completion
30 th November 2008
 
 
Works Contract
Contract No 2 (S-1210)
Date of Contract signing
13th December 2007
Contractor
AB „Panevėžio keliai“
Value of works carried out
47,075,376.24 LTL
Date of completion
30 th November 2008
 
 
Works Contract
Contract No 3 (S-47)
Date of Contract signing
Contractor
nd March 2009
AB „Panevėžio keliai“
Contract Price
44,014,101.17 LTL
Date of completion
30 th November 2009
 
Updated 01-10-2009
top
Development of Road E67 (VIA BALTICA) of Transeuropean Road Network
 
Project „Development of Road E67 (VIA BALTICA) of Transeuropean Road Network. Completion of Road Strengthening and Reconstruction of Marvelė intersection“
 
The project is financed from the European Union Structural Assistance funds 2007–2013 according to the Economic Growth Action Plan Priority 5 “Development of Trans-European Transport Networks“  instrument VP2-5.1-SM-01-V “Enhancement of the Permeability of Trans-European Road Infrastructure. Improvement of Technical Parameters".
 
I Transport Corridor (VIA BALTICA) cross the territory of Lithuania in the south-north direction connecting two posts of border crossing of Lithuanian Republic - Saločiai and Kalvarija. In the territory of Lithuanian Republic five main roads constitute the I Transport corridor: A10 Panevėžys–Pasvalys–Ryga, A17 Panevėžys bypass, A8 Panevėžys–Aristava–Sitkūnai, A1 Vilnius–Kaunas–Klaipėda, A5 Kaunas–Marijampolė–Suvalkai. This Corridor goes with European Road E67 and on the separate sections – with other Transport Corridors of all Europe: with Transport Corridor IXB - on the Road A1 section from 102,04 km to 114,54 km; with Transport Corridor IXD - on the Road A5 section from 0,0 km to 63,76 km;
 
After completion of works in the period of years 2004-2006 on this transport corridor the number of sections, which did not correspond the requirements was reduced; however the main problem remains on the sections with still increasing traffic volume. After having evaluated possible alternatives and especially when traffic of freight vehicles is still on the increase an utmost attention in the stage of years 2007-2009 will be paid for reinforcement of roads’ cover and reconstruction of dangerous intersection.
 
The main objectives of the project:
 
-         reconstruction and reinforcing of  road cover, degraded due to the increased traffic volume;
-         implementation of missing traffic safety measures and  reconstruction of the actual;
-         reconstruction of crossing which causes biggest problems; reduction of negative road impact upon the environment;
 
Cost of project
93,358,000 LTL
including:
 
  • Cohesion Fund
62,4332,000 LTL
 
  • Road Maintenance and Development programme
  
30,925,000 LTL
 
Start date of Project
 
14 September 2007
End date of Project
March 2010
 
The Project includes:
-         strengthening of road pavement – 27.33 km;
-         reconstruction of Marvele intersection – 1 unit;
-         construction of deceleration acceleration lane - 0.323 km;
-         construction of wire net fencing – 5.02 km;
-         construction of pedestrian – cycling paths – 2,99 km.
 
 
Contracts of the Project
 
Five contracts were signed.
 
Contracts data
 
Works Contract
Contract No 1 (S-1195)
Date of Contract signing
03 December 2007
Contractor
AB Kauno tiltai
Value of works carried out
45,630,657 LTL
Date of completion
31 October 2008
 
Works Contract
 
Additional Contract to Contract No 1 (S-1098)
Date of Contract signing
26 August 2008
Contractor
AB Kauno tiltai
Value of works carried out
931,828 LTL
Date of completion
31 October 2008
 
Works Contract
Contract No 2 (S-1407)
Date of Contract signing
10 December 2008
Contractor
AB Kauno tiltai
Value of works carried out
25,232,684 LTL
Date of completion
15 November 2009
 
Works Contract
Contract No 3, Lot I (S-235)
Date of Contract signing
13 July 2009
Contractor
AB Panevezio keliai
Value of works carried out
6,395,870 LTL
Date of completion
30 November 2009
 
Works Contract
Contract No 3, Lot II (S-236)
Date of Contract signing
13 July 2009
Contractor
AB Panevezio keliai
Value of works carried out
15,179,609 LTL
Date of completion
30 November 2009
Updated 28-04-2010
top
Reconstruction of Road E85 (Vilnius–Kaunas–Klaipėda) of the Transeuropean Road Network. Construction of Skyway in the Direction of Kaunas–Klaipėda and Klaipėda–Kaunas at the Jakai Junction
 
Reconstruction of Road E85 (Vilnius–Kaunas–Klaipėda) of the Transeuropean Road Network. Construction of Skyway in the Direction of Kaunas–Klaipėda and Klaipėda–Kaunas at the Jakai Junction
 
The project is financed from the European Union Structural Assistance funds 2007–2013 according to the Economic Growth Action Plan Priority 5 “Development of Trans-European Transport Networks“  instrument VP2-5.1-SM-01-V “Enhancement of the Permeability of Trans-European Road Infrastructure. Improvement of Technical Parameters".
 
The Jakai roundabout is an entrance gate to Klaipėda, the most northern ice-free port of the Baltic Sea, and the only port in the Republic of Lithuania. It is also the distribution point of the flows of holidaymakers coming to the Lithuanian seaside. It is one of the most important regions in the road infrastructure of Lithuania as it contains one of the largest local and transit traffic flows of goods and passengers. The main part of these flows is distributed on the roads Vilnius–Kaunas–Klaipėda, Klaipėda–Liepaja and Kaunas–Jurbarkas–Klaipėda, which cross at the Jakai junction. The junction is also part of IXB Transport Corridor which is an important connection in the European Union.
 
The goal of the project is to reconstruct the road sections which do not meet the requirements set for transport corridors as well as to ensure safe and comfortable traffic conditions conforming to the level of traffic volumes, the road significance and international standards.
 
When the Jakai roundabout reconstruction works are completed, the infrastructure of roads, joining European transport corridors, will be improved and the following benefits will be achieved:
·          Improved image of Lithuania as a transit country
·          Improved traffic conditions, especially during the summer season
·          Reduced negative environmental impact
·          Reduced accident rate
·          Improved business conditions in the Klaipėda free economic area and in the seaside region
·          Reduced vehicle operating costs.
 
 
The following works will be completed under this project:
 
-         Construction of a new road – km 1.02
-         Reconstruction of the existing road – km 0.34
-         Construction of a new skyway (length km 0.61) of four traffic lanes
-         Construction of a tunnel viaduct (length km 0.024)
-         Installation of traffic lights in a tunnel
-         Reconstruction of road engineering networks and installation of lighting on the Jakai junction.
 
Works Contract
Contract  No S-1348
Date of Contract Signing
13/11/2008
Contractor
AB Kauno tiltai
Value of Contract
  Estimated Part of Cohesion Fund
99,752,659.70 LTL
    35,768,000 LTL
Date of Completion
 
30/11/2010
 
 
Updated 01-10-2009
top
Reconstruction of Road E77 (Riga–Šiauliai–Tauragė–Kaliningrad) of the Transeuropean Road Network
 
Reconstruction of Road E77 (Riga–Šiauliai–Tauragė–Kaliningrad) of the Transeuropean Road Network
 
The project is financed from the European Union Structural Assistance funds 2007–2013 according to the Economic Growth Action Plan Priority 5 Development of Trans-European Transport Networks instrument VP2-5.1-SM-01-V Enhancement of the Permeability of Trans-European Road Infrastructure. Improvement of Technical Parameters.
 
IA Transport Corridor (road E77 (A12) Riga–Šiauliai–Tauragė–Kaliningrad) is an important connection in the Lithuanian and TEN-T road infrastructure. This road connects Riga (the capital of Latvia) with Gdansk (Poland) through Kaliningrad area in the direction of north-south. Despite of visa regime, which was established between Lithuania and Kaliningrad region, on 1 July 2003, the relationships in the field of tourism and trade are being developed. Thus it is very important to reconstruct the road for safer and more comfortable transit traffic on IA Transport Corridor. It is necessary to widen the road, to strengthen road pavement and to implement road safety measures.
 
The goal of the project is to reconstruct the road sections which do not meet the requirements set for transport corridors as well as to ensure safe and comfortable traffic conditions conforming to the level of traffic volumes, the road significance and international standards.
 
When the Project works are completed, the following benefits will be achieved:
– Improved image of Lithuania as a transit country
– Improved traffic conditions, especially for vehicles travelling from Latvia to Poland and other European countries
– Reduced negative environmental impact
– Reduced accident rate
– Width of road pavement conforming to the technical requirements
– Strengthened road pavement construction from 10 to 11.5 tonnes axle loading
– Slower pavement degradation and longer pavement service life
– Lower costs of road repair and routine maintenance
– Reduced vehicle operating costs
– Reduced travelling time.
 
The following works will be completed under this project:
– Reconstruction of the existing road – km 7.8
– Reconstruction of 2 intersections
– Construction of pedestrian and cycling paths – km 7.71
– Construction of road illumination – km 1.5.
 
 
Primary cost of Project
41.933 million LTL
                      including:
 
Cohesion Fund
39.995 million LTL
Road Maintenance and Development Programme
1.937 million LTL
Start date of Project
15/10/2007
Primary End date of Project
03/2010
 
 
Contracts of the Projects:
 
Works Contract
Contract No S-871
Date of Contract Signing
01/07/2008
Contractor
AB Kauno tiltai
Value of Works carried out
5,997,226 LTL
Date of Completion
30/05/2009
   
   
Works Contract
Contract No S-1315
Date of Contract Signing
05/11/2008
Contractor
UAB Šiaulių plentas
Value of Works carried out
32,125,271 LTL
Date of Completion
30/11/2009
   
   
Services Contract (Preparation of Technical Design)
Contract No S-1063
Date of Contract Signing
15/10/2007
Services supplier
UAB Kelprojektas
Value of Works carried out
793,899 LTL
Date of Completion
31/03/2008
   
   
Services Contract (Preparation of Technical Design)
Contract No S-7
Date of Contract Signing
09/01/2008
Services supplier
UAB Kelprojektas
Value of Works carried out
558,401 LTL
Date of Completion
29/02/2008
 
Updated 26-01-2010
top
Project „Development of the roads E85 (Vilnius–Lida) and E272 (Vilnius–Panevėžys–Šiauliai–Palanga) of the Transeuropean Network. Reconstruction of section Šiauliai–Radviliškis of the road Panevėžys–Šiauliai (Stage I)“
 
Project „Development of the roads E85 (Vilnius–Lida) and E272 (Vilnius–Panevėžys–Šiauliai–Palanga) of the Transeuropean Network. Reconstruction  of section Šiauliai–Radviliškis of the road Panevėžys–Šiauliai (Stage I)“
 
The project is financed from the European Union Structural Assistance funds 2007–2013 according to the Economic Growth Action Plan Priority 5 Development of Trans-European Transport Networks“ instrument VP2-5.1-SM-01-V Enhancement of the Permeability of Trans-European Road Infrastructure. Improvement of Technical Parameters.
 
Roads  E85 (Vilnius–Lida) and E272 (Vilnius–Panevėžys–Šiauliai–Palanga) of Trans-European Network cross Lithuania from south east to west, connecting the Lithuanian borderline office in Šalčininkai with western Lithuania. European road E272 in Lithuania starts on the seaside and reaches Vilnius through Šiauliai and Panevėžys. In Šiauliai transport corridor IA, leading to Riga, in Panevėžys Via Baltica (I transport corridor), leading to Riga and Tallinn, as well as an important road Panevėžys–Daugavpils, leading to Latvia and Russian Federation (Saint Petersburg) integrate into this road. In Vilnius, it is crossed by transport corridor IXB, leading to Minsk and Moscow. Road E85 from Vilnius continues to the Lithuanian border with Belarus and crosses the territories of Belarus, Romania and Greece.
 
The project is focused on the development of roads E85 (Vilnius–Lida) and E272 (Vilnius–Panevėžys–Šiauliai–Palanga) of Trans-European Network. As traffic volumes have been increasing on these roads, they shall be upgraded ensuring safe and comfortable traffic conditions meeting the level of traffic volumes, the road significance and international standards.
 
When the Project works are completed, the following benefits will be achieved:
·           improved image of Lithuania as a transit country;
·           improved traffic conditions;
·          width of road pavement conforming to the technical requirements;
·          strengthened road pavement construction from 10 to 11.5 tonnes axle loading;
·          reduced accident rate;
·          reduced vehicle operating costs;
·          slower pavement degradation and longer pavement service life;
·          lower costs of road repair and routine maintenance;
           reduced negative environmental impact;
           reduced travelling time.
 
 
The Project includes:
 
-         reconstruction of 6.51 km of road pavement;
-         construction of 1.39 km of pedestrian and cycling paths;
-         construction of 5.23 km of access road with pedestrian and cycling paths;
-         construction of 4.84 km of access road without pedestrian and cycling paths;
-         construction of 1.37 km of access roads in junctions;
-         construction of roundabout;
-         construction of tunnel for pedestrians and vehicles;
-         construction of 657 metres of noise barrier;
-         construction of underground pedestrian passageway;
-         construction of tunnel viaduct;
-         erection of 2.44 km of installation;
-         erection of 914 metres of fence for the protection of amphibians.
 
  
Cost of Project
92,516,593  LTL
including:
 
  • EU funds
79,739,234 LTL
 
 
  • Road Maintenance and Development programme
12,777,359 LTL
 
 
 
 
Start date of Project
21/08/2009
End date of Project
04/2011
 
 
Contracts of the Project
 
 
Works Contract
Contract No 1 (S-425)
Date of Contract signing
21 August 2009
Contractor
UAB Šiaulių Plentas
Contract price
82,082,253.21 LTL
Date of completion
21 December 2010
 
 
Updated 21-05-2010
top
Project „Development of Road E262 (Kaunas–Zarasai–Daugpilis) of the Transeuropean Network. Road Pavement Reconstruction“
 
 Project „Development of Road E262 (Kaunas–Zarasai–Daugpilis) of the Transeuropean Network. Road Pavement Reconstruction“
 
The project is financed from the European Union Structural Assistance funds 2007–2013 according to the Economic Growth Action Plan Priority 5 “Development of Trans-European Transport Networks“  instrument VP2-5.1-SM-01-V “Enhancement of the Permeability of Trans-European Road Infrastructure. Improvement of Technical Parameters".
  
International corridors crossing our country are the main part of the Lithuanian road network. Road E262 of the Transeuropian network, merging on Lithuanian territory with main road A6 Kaunas–Zarasai–Daugpilis, is one of the links of network of the European transport corridors. There are still some sections of this road falling behind the requirements for international roads. The main objective of the project is the improvement of road technical parameters, adapting them to the growing traffic volume, the improvement of traffic conditions, the preservation of harmony with environment..
 
After performing of works foreseen in the strategic development programmme for road E262 of the Transeuropian network the following benefits will be achieved:
·          improved image of Lithuania as a transit state;
·          improved road traffic conditions;
·          reduced accident rate;
·          reduced vehicle operating costs;
·          slower pavement degradation and longer pavement service life;
·          lower costs of routine maintenance.
 
 
Preliminary Cost of Project
140,772,754 LTL
including:
 
  • EU Funds
125,728,882 LTL
  • Road Maintenance and Development programme
15,043,872 LTL
Start date of Project
23/03/2010
End date of Project
31/12/2011
 
The project includes:
 
-        reconstruction of 31.34 km road pavement;
-        construction of 0.664 km of pedestrian and cycling paths;
-        construction of traffic-light control at the road intersections to Išorai, Zatyšiai and Stašėnai;
-                                   construction of 20.5 km wire net fencing;
-         installation of 1.28 km illumination;
-         construction of underground pedestrian passageway;
-         reconstruction of 2 bridges.
 
Contracts of the Project
 
Works Contract
Contract No 1 (S-132)
Date of Contract signing
9th  April 2010
Contractor
AB „Panevėžio keliai“
Contract price
76,227,914.89 LTL
Estimated date of completion
26 th January 2011
 
 
Works Contract
Contract No 2 (S-343)
Date of Contract signing
28th June 2010
Contractor
UAB „Fegda“
Contract price
39,785,583.67 LTL
Estimated date of completion
2 nd July 2011
   
Works Contract
Contract No 3 (S-84)
Date of Contract signing
23rd March 2010
Contractor
AB „Panevėžio keliai“
Contract price
23,580,020.68 LTL
Estimated date of completion
30 th November 2010
 
 
Technical Supervision Contract
Contract No S-77
Date of Contract signing
Contractor
20th March 2010
UAB „Kelvista“
Contract price
2,033,574.52 LTL
Updated 26-07-2010
top
Project Nr. VP2-5.1-SM-01-V-01-010 Reconstruction of Road E85 (Vilnius–Kaunas–Klaipėda) of the Transeuropean Road Network. Construction of Skyway in the Direction of Kaunas–Klaipėda and Klaipėda–Kaunas at the Jakai Junction
 
Project Nr. VP2-5.1-SM-01-V-01-010 Reconstruction of Road E85 (Vilnius–Kaunas–Klaipėda) of the Transeuropean Road Network.
Construction of Skyway in the Direction of Kaunas–Klaipėda and Klaipėda–Kaunas at the Jakai Junction
 
The Jakai roundabout is an entrance gate to Klaipėda, the most northern ice-free port of the Baltic Sea, and the only port in the Republic of Lithuania. It is also the distribution point of the flows of holidaymakers coming to the Lithuanian seaside. It is one of the most important regions in the road infrastructure of Lithuania as it contains one of the largest local and transit traffic flows of goods and passengers. The main part of these flows is distributed on the roads Vilnius–Kaunas–Klaipėda, Klaipėda–Liepaja and Kaunas–Jurbarkas–Klaipėda, which cross at the Jakai junction. The junction is also part of IXB Transport Corridor which is an important connection in the European Union.
 
The goal of the project is to reconstruct the road sections which do not meet the requirements set for transport corridors as well as to ensure safe and comfortable traffic conditions conforming to the level of traffic volumes, the road significance and international standards. When the Jakai roundabout reconstruction works are completed, the infrastructure of roads, joining European transport corridors, will be improved and the following benefits will be achieved:
·                     Improved image of Lithuania as a transit country
·                     Improved traffic conditions, especially during the summer season
·                     Reduced negative environmental impact
·                     Reduced accident rate
·                     Improved business conditions in the Klaipėda free economic area and in the seaside region
·                     Reduced vehicle operating costs.
 
The following works will be completed under this project:
·                     Construction of a new skyway (length km 0.317) in the direction of Kaunas–Palanga on the second level
·                     Construction of a new skyway (length km 0.552) in the direction of Palanga–Kaunas on the third level
·                     Construction of a new road and reconstruction of the existing road – km 4.54
·                     Construction of pedestrian and cyclists paths (length km 1.55)
·                     Construction of noise barriers (length km 1.10)
·                     Reconstruction of road engineering networks and installation of lighting on the Jakai junction.
 
Works Contract
Date of Contract Agreement signing
Contractor
Value of Contract
Estimated Part of Cohesion Fund
Date of Completion
S-763
17/12/2010
AB Kauno tiltai
58,798,658 LTL
58,431,980 LTL
30/11/2012
Technical Supervision Services Contract
Date of Contract Agreement signing
Supervises Provider
Value of Contract
Estimated Part of Cohesion Fund
Date of Completion
S-745
09/12/2010
VĮ Problematika
1,810,091 LTL
1,810,091 LTL
31/01/2013
 
top
Reconstruction of Road E85 (Vilnius–Kaunas–Klaipėda) of Transeuropean Road Network. Reconstruction of the road section through Grigiškės (Stage II)
 
 
 
Reconstruction of Road E85 (Vilnius–Kaunas–Klaipėda) of Transeuropean Road Network. Reconstruction of the road section through Grigiškės (Stage II)
 
The project is financed from the European Union Structural Assistance funds 2007–2013 according to the Economic Growth Action Plan Priority 5 “Development of Trans-European Transport Networks“ instrument VP2-5.1-SM-01-V “Enhancement of the Permeability of Trans-European Road Infrastructure. Improvement of Technical Parameters".
 
Road A1 Vilnius–Kaunas–Klaipėda is the part of Pan-European IXB transport corridor and the main transport connection between East and West. The reconstruction of road section 13.30–19.60 km is urgent in order to fit TEN-T network roads to increasing traffic volume. This road section crosses the Grigiškės residential area. Huge transport flows from Grigiškės and other surrounding residential areas as well as intensive international transit flows take this road section to Vilnius. Intensive pedestrian and cyclist traffic moves along this road section.
 
When implementing the project, the road section crossing Grigiškės is reconstructed into a 6-traffic-lane road. The following works are being carried out: pavement is strengthened and widened, new connecting roads are constructed, the bridge is reconstructed, a grade-separated intersection, underground crossings, walkways and cycle tracks are constructed and other traffic safety and environmental protection measures are implemented. The following benefits will be gained upon the project implementation:
  • improved traffic conditions;
  • reduced accident rate;
  • reduced vehicle operating costs;
  • improved transit traffic conditions,
  • shorter travelling time;
  • reduced environmental impact.
 
 On 18 February 2011 the Agreement of financing and administration of the project No VP2-5.1-SM-01-V-01-007 “Reconstruction of Road E85 (Vilnius–Kaunas–Klaipėda) of Transeuropean Road Network.  Reconstruction of road section through Grigiškės (Stage II)”  No 1F-33 was signed between the Lithuanian Road Administration under the Ministry of Transport and Communications, Transport Investment Directorate and the Ministry of Transport and Communications of the Republic of Lithuania.
 
 
Cost of Project
36,739,485 LTL
including:
 
     EU funds
26,720,766 LTL
   
     Road Maintenance and Development programme
10,018,719 LTL (expenditures not eligible for EU financing)
   
   
Start date of Project
10/01/2011
End date of Project
31/05/2012
 
The Project includes:
  • reconstruction of road pavement – 4.5 km;
  • construction of pedestrian-bicycle path – 1.3 km;
  • reconstruction of bridge – 1 unit;
  • implementation of traffic safety and environment protection measures.
 
 
Contracts of the Project
   
 
Works Contract
Contract No 1 (S-12)
Date of Contract signing
10 January 2011
Contractor
UAB Fegda
Value of works carried out
33,749,634.30 LTL
Date of completion
30 November 2011
   
 
Service Contract
(Technical Supervision)
Contract No S-23
Date of Contract signing
18 January 2011
Supplier
VĮ Problematika
Value of the contract
1,069,000.87 LTL
Date of completion
31 January 2012
 